VCU Community Memorial Hospital

Customer: DPR Construction

Architect: SmithGroup, Inc.

Engineer: Leach Wallace Associates

Owner: Virginia Commonwealth University

Year Completed: 2017

Area: 166,700 SF

Market: Commercial

Sector: Healthcare

Contract Amount: $13M

PROJECT DESCRIPTION

ACI designed and constructed pre-manufactured piping, electrical, and wood blocking in a panelized wall system, which was then transported to the site and installed in the patient rooms. Other pre-fabricated efforts on the project included skids and piping for the boiler and chiller plant that were shop-fabricated and shipped fully assembled to the site.

What would normally take months, took only days in the field.

PROJECT HIGHLIGHTS

  • 600 TONS of Cooling
  • 5 RTU’s – 150,000 CFM
  • Prefabricated Med Gas Walls
  • Prefabricated Modular Central Utility Plant
  • Nearly 300 VAV’s
  • 3 Boilers with a Capacity of 9000 MBH
  • 100 HP Steam Generator
  • LEED Silver Certification